亚洲天堂

Skip to content
Sponsored Content

Coastal GasLink uses state-of-the-art method to cross waterway

Micro-tunneling method selected as safest and most advanced way to cross beneath the Morice River
26767303_web1_211011-Impress-TST-CoastalGasLink_1
The Morice River micro-tunnel will be the fifth trenchless water crossing for the Coastal GasLink Project, all of which were completed with zero safety incidents.

On top of navigating some of the most rugged and beautiful terrain in B.C., the Coastal GasLink project鈥檚 670 km project route crosses many waterways. Each crossing is treated with the utmost care and respect, with many months of preparation by teams of experts to determine the safest way to cross.

鈥淲e take very seriously, both because of their intrinsic environmental value and also because they support the diverse communities Coastal GasLink passes through,鈥 said Adair Rigney, Coastal GasLink鈥檚 team lead of environmental planning & permitting.

The project鈥檚 crossing of the Morice River near Houston, B.C. is no exception. 鈥淏efore construction begins, we gather extensive information through a variety of assessments to select the safest and most appropriate . Everything from water flow, bank stability, fish presence and habitat, constructability, and regulatory requirements are carefully considered,鈥 added Adair.

After carefully examining the data collected, the project selected the trenchless micro-tunneling method to cross beneath the Morice River. The state-of-the-art method uses hydraulic jacks and a tunnel boring machine to install concrete segments deep below the water body without coming into contact with the river or any of its channels.

Pipe is then safely pulled through the tunnel created by the concrete segments and then the tunnel and pipe are carefully tested and sealed. The advanced micro-tunneling method is uniquely suited for the ground conditions around the Morice River. It requires minimal excavation, is highly precise, and has minimal environmental disturbance without ever affecting the flow of the river.

Throughout the process, local Indigenous community members will be on site to monitor construction activities and report back to their communities through the .

Once completed, the Morice River micro-tunneling crossing will be Coastal GasLink鈥檚 fifth trenchless water crossing and one of thousands of crossings throughout B.C., all operating safely under rivers and streams of all sizes.

For Tommy Adair, Lead Environmental Inspector for Sections 5, 6, and 7, the proven legacy of micro-tunneling and trenchless crossings speak to the extraordinary lengths the project goes to protect our waterways. 鈥淭renchless crossing methodologies are effective and safe. They鈥檝e become an industry standard for more significant crossings such as the Morice River.鈥

鈥淭he way that the river鈥檚 flowing now, it鈥檚 flowed for centuries. We plan for it to remain that way for centuries more.鈥

Micro-tunneling is a state-of-the-art trenchless crossing method that allows the pipe to be safely installed under the Morice River.
Micro-tunneling is a state-of-the-art trenchless crossing method that allows the pipe to be safely installed under the Morice River.

Micro-tunneling is a state-of-the-art trenchless crossing method that allows the pipe to be safely installed under the Morice River.

Learn more about how Coastal GasLink is protecting our waterways and environment by visiting .



About the Author: Black Press Media Staff

Read more

(or

亚洲天堂

) document.head.appendChild(flippScript); window.flippxp = window.flippxp || {run: []}; window.flippxp.run.push(function() { window.flippxp.registerSlot("#flipp-ux-slot-ssdaw212", "Black Press Media Standard", 1281409, [312035]); }); }