Coastal GasLink has asked for land use support from the Regional District of Bulkley Nechako (RDBN) for its Segundo Lake compressor plant.

The request came at the RDBN board鈥檚 meeting Oct. 26.

Nicole Stuckert, CGL鈥檚 team lead on land for B.C. projects said approximately six to ten hectares of land for workforce accommodations and six hectares of temporary workspace to support the construction of this compressor 鈥 one of four to be built along the pipeline鈥檚 670-kilometre route 鈥 are required.

The Segundo Lake compressor plant is to be built between 亚洲天堂 Lake and Fraser Lake.

She said the 16 hectares are necessary for safe and efficient project execution and to allow for sufficient accommodations for workers and space for equipment.

Natasha Westover, public affairs manager from CGL, said the purpose of the compressor plant was to re-pressurize the flow of natural gas along the pipeline in specific locations when the pressure drops due to friction.

In order to aid their land use decision, Mark Parker, chair of the RDBN board, asked the representatives of CGL if the company would develop infrastructure for broadband internet and traffic right-of-ways on highways, and make some investments in the Northwest Invasive Plant Council.

He would also appreciate it if CGL could persuade 45 medical professionals out of the current 90 to stay behind.

Ian McLeod, senior community and socio-economic advisor for CGL noted that their projects have an agreement with 鈥業nternational SOS,鈥 which provides paramedics and nurse practitioners at their lodges.

鈥淪o, as of summer 2023, we had 90 medical personnel available to assess and advise project employees. We also liaise with Northern Health to ensure and manage local health care facilities.鈥

McLeod also mentioned that Northern Health has already requested to increase the availability of nurse practitioners, and CGL created a 24-hour availability at the Huckleberry work camp and 7 Mile Lodge.

Tanner Moulton, public affairs advisor of TC Energy (CGL鈥檚 parent company) addressed the invasive plant issue.

鈥淎bsolutely deja vu, I think we鈥檝e had this conversation in the earlier days of the project,鈥 he said. 鈥淪o, I had the pleasure of working with the Northwest Invasive Plant Council years ago, and they鈥檝e been engaged in our project as well. We鈥檙e happy to restart those conversations again.鈥

Parker also has concerns about the final investment decision by the project for the Segundo Lake compressor station. He questioned what might change that final investment decision after the board spent a year and a half going through the process of providing the land.

Stuckert said LNG Canada decides how the project proceeds and provides details on final investment decisions.

鈥淪o right now, we鈥檝e been given the go-ahead to get all the permits in place and be ready,鈥 Stuckert said.

鈥淚f something didn鈥檛 happen, we would have a significant strategy to do our engagement and cancel things or go through those processes at that time. Still, we鈥檙e very positive and hopeful about how things are going.鈥

Moulton also mentioned that the first phase of 7 Mile Lodge鈥檚 demobilization has begun, and the land reclamation process will soon begin.

After the presentation, the board said it appreciated the updates, but it is not ready to make a decision on providing the land.